We are headed south into Carroll County, KY Monday to begin a very serious Deck Rescue Painting project that we want you to follow

The deck in question spans the back of a house and has sunk down in several areas to post movement. 

That’s only a part of the problem however. It’s also on top of that a very weathered dilapidated structure that needs tons and tons of Restoration and Repair. That’s before we can even begin to think about Breaking out the World’s Toughest, Most Advanced, Deck Resurfacing Coating Kong Armor and Armor Encapsulating it for Life!

I’ll put it to you this way: We would like for you to follow this project because we believe once you see the power of our Deck Rescue Painting service and how it brings back a deck On the actual verge of Replacement and falling over, you won’t be able to deny that we can HELP YOU DO THE SAME WITH YOUR DECK. 

PROOF IS POWERFUL. AND WE WANT YOU TO SEE THE PROOF! 

WE WANT YOU TO SEE THAT YOU DONT NEED DECK REPLACEMENT 

WE WANT YOU TO SEE THAT OUR LIFETIME DECK ARMOR IS TRULY THE MOST ADVANCED AND CAPABLE DECK RESURFACING COATING ON THE PLANET TODAY!

I know for certain that PROOF will play out here. Because I won’t let it not play out. And I want you to see that too.

I will update this blog post right here as the project moves forward. 


UPDATE

JULY 8TH, 2024

Today we were able to get into Carollton, KY and begin the Deck Rescue Painting Project. The very first task was changing the deck post. Here is a intro video I took this morning!

Within minutes of recording this intro video the Deck Rescue Painter’s already had the first area of the deck supported temporarily and swapped out the first bad Post. This was the post that sunk and was causing the floor unevenness.

2 Hours later we had Every Post Replaced and added 2 additional post for extra structural integrity for this long deck. Keep in mind the old Deck Post were 4×4, We are Replacing then with 6×6 Post that are much thicker and stronger. The additional 2 Post are likely overkill, but we want to ensure this deck doesn’t drop ever again.

We thought about adding another post right there where the stairs are at but think it will make traversing the stairs from the porch underneath odd. So we opted to leave it how it was through there.

As you can see in the Deck Restoration Painters / Deck Rescue Painters of Kong Armor ™️ do not play around. Within 3 hours of project start today this deck had all new post.

They are now currently Restoring the Steps and Washing this deck as the day closes out here. It’s currently 6:23 pm as I write this. I am positive the deck is no longer in danger of collapsing or needing replacement.

We still have a long way to go. It still needs more Restoration and then Peeling Deck Paint LockDown Encapsulation. But, will get there.

Stay tuned for the next Project update as We Prove to you that YOU DONT NEED DECK REPLACEMENT.

YOU WILL BE SHOCKED AT HOW GORGEOUS AND SOUND THIS DECK TURNS OUT. YOU WONT WANT TO MISS THIS DECK ARMOR TRANSFORMATION!

Ps…. this project has been named it’s the #sixpostdeck.


UPDATE JULY 9TH

Today the Deck Rescue Painter’s beat the rain into Carrolton and we were able to get the bad and rotten floor boards replaced, and the rails are restored now for the most part.

Rain 🌧 has started falling at the project and so we are closing it down for the day.

In just 24 short hours we’ve ended the danger of collapse by replacing the deck post, weve completely restored the decks rails, and replaced over 20 deck boards.

We just have a tiny bit of Restoration left to do on our next visit. Then will be moving on to the Resurfacing of this Absurdly Weathered Deck. And the Lockdown Encapsulation of the Peeling Deck Paint Problem it has. Standbye for Lockdown

AND REMEMBER THE PURPOSE OF THIS POST IS TO SHOW YOU THAT NO MATTER HOW BAD OF A CONDITION YOUR DECK IS IN YOU DONT NEED REPLACEMENT. YOU NEED RESTORATION AND RESURFACING VIA THE WORLDS TOUGHEST DECK ARMOR – KONG ARMOR …..remember that. Cause from here things are about to get real your going to see the power 🔋 of a real Deck Coating 🦍

TAKE THE TIME RIGHT NOW TO SUBSCRIBE TO OUR BLOG AS A EMAIL NEWSLETTER USING THE WIDGET BELOW!

UPDATE JULY 12TH 2024

Over the last couple of days the #sixpostdeck project has been suspended for rain and inclement weather . However today we finally have a video update. Additionally we should see a finish tommorow July 13th

Update July 17th 2024


Hey Guys sorry for updating this behind schedule but we reached Completion on the #sixpostdeck on July 13th! It is a completely different structure Now!

A strong, stable, indefinitely viable, Supremely Resurfaced and Armor Protected Deck system stands where the old weather battled collapsing deck used to be.

The old 4×4 Deck Post that were barely holding the Deck from collapsing are gone and in there place is new Ultra Thick 6×6 Deck Post. Instead of just replacing the 4 post that were present, We opted to replace those plus add two additional more to ensure our customer never has to worry about this again! Plenty of Support and Load distribution. You could park a Dump Truck on this Carrollton, KY deck now without issue!

The Steps that were wobbling and collapsing everywhere are now firmly anchored via new post, and a connection to one of the New 6×6 post. They are like walking up and down a Concrete Steps. They are firm solid and without one ounce or hint of weakness!

The steps have underside step treads to protect against step failure and we also Added Simpson- Strong Tie braces to the Steps Connection